Interior Footings Dug
May 28- June 11, 2021
Interior footings were dug in Area D by the loading dock as well as Smith Excavation compacting footings for the retaining wall at the loading dock. Bouten crew was busy forming concrete footings in Area F waiting room. The main pluming waste line was installed by Mack & Little through Area F corridor.