Interior Footings Dug

May 28- June 11, 2021

Interior footings were dug in Area D by the loading dock as well as Smith Excavation compacting footings for the retaining wall at the loading dock. Bouten crew was busy forming concrete footings in Area F waiting room.  The main pluming waste line was installed by Mack & Little through Area F corridor.