Making Headway

June 25- May 11, 2021

Underground plumbing,  electrical, and concrete foundation forming and rebar continued throughout the week.  At the South-West side of the site, Smith excavation dug dry wells. Mack and Little began backfilling the decontamination take in Area E.  The Bouten Crew was busy pouring the MRI dock footings and installing form work and rebar in Area A.